Much continues to change since our last update from three months ago. The locker rooms have exterior and interior walls and poured floors and the ground floor of the main building shows foundations and awaits more concrete. Rumor has it that much of the steel framework will start shortly.
Check out the bird’s eye views—can you find the blue painted “Rocks” (that will be along the front of the new school), the water tower (can we paint “Dulaney” on that?) and the blue of Loch Raven Reservoir in the background?
The number one question that we get asked by Dulaney alums is:“Do the seniors still paint the rocks at Dulaney? ”Answer: You betcha!
Continuing the tradition for over 60 years (and 60 plus coats of paint), the Class of 2027 had an awesome Senior BBQ and even got some paint on the rocks on a day that was great to be a Lion!PS: Remember that, despite the construction of the new Dulaney, the ROCKS are going nowhere.
Dulaney HS - Construction Updates
October 2025 Update:
Project has begun construction – Sitework is underway
November 2025 Update:
Site demolition underway
Sediment and erosion control in progress
Staging and laydown areas in progress
January 2026 Update:
Sitework ongoing
Grading and site demolition
Underground utility installation
Sediment and erosion control in progress
Site grading in progress
Staging site logistics in progress
February 2026 Update:
Underground stormwater and Sand filtration system ongoing
Site demolition continuing
Underground Utility work in progress
Site utilities underway
March 2026 Update:
Site drive lanes and parking underway
Building pad subgrade underway
Foundations underway
Site utilities in progress
Retaining walls nearing completion
June 2026 Update:
Stormwater management work ongoing
Transformer and Pad have been set by BGE
Fencing installation underway
Curb/Gutter/Sidewalk in progress
Site utility work ongoing
Site retaining walls in progress
Building foundations underway
Under slab rough-ins in progress
July 2026 Update:
Sitework – grading, utilities, and retaining walls ongoing
Lower-Level Area A in progress – PE area
Crane for structural steel being built
Building footings ongoing
Underground utilities in progress
September 2026 Update:
Footings complete through area D and G.
Slab on grade poured through area D.
Gym masonry walls ongoing. Masonry walls for auditorium started.
Structural steel started for gym. Girders and joists in place.
Light rain shower, with a high of 80 and low of 58 degrees. Don't forget your umbrella! Light rain shower during the morning, sunny for the afternoon, patchy light rain for the evening, light drizzle overnight.